Records the City of Kenyon released on October 26, 2026 in response to data requests of October 15 and October 22 under the Minnesota Government Data Practices Act, with an inventory of every file and a comparison against the account the city administrator gave the council on October 13. Prepared by kenyonminnesota.com. Not indexed.
| Item | Requested | Result |
|---|---|---|
| A1 | KMU service application and specification agreement for 551 Engel Dr | Nothing. An Oct 14 CMPAS meeting invite is titled "Assist with filling out City service applications." |
| A2 | The "July 2 contract" described Oct 13 as unsigned | Partial. It is the CMPAS Master Distribution Services Agreement, a template sent to every member utility; Lehner's Oct 12 email: "Was sent to Randy in July." |
| A3 | CMPAS correspondence, 2026 | Partial. Oct 5 to 21 only, plus an Oct 20 forward of a May 13 Xcel/CMPAS meeting summary. |
| A4 | Transformer and substation estimates | Partial. A $38,250 lot estimate from Jan 2026. No purchase order, no substation estimate, nothing behind $1M or $3 to 6M. |
| A5 | KMU minutes and packets, 2025 to present | Partial. Minutes complete; no 2025 agendas; no packets. |
| A6 | Five City-KMU agreements and org chart | Complete. |
| A7 | Falcon purchase agreement, assignment, price | Partial. Price $212,000; the Firebird-to-Falcon assignment is an unsigned draft dated "March ___, 2026." |
| A8 | EDA minutes and packets, 2026 | Partial. No Aug 25 packet. |
| A9 | Administrator employment agreement, salary changes | Partial. Unsigned Word draft; $125,500 at hire; no changes produced. |
| A10 | Res 2026-34 separation terms | Complete. Resignation effective Dec 9, 2026; paid leave to Oct 12; insurance to Dec 31. |
| B1, B2 | OCM certification requests and City certifications for the cannabis business | Nothing, and no statement that none exists. |
| B3 | Correspondence with the cannabis companies on electric service | Substantial, all from the EDA coordinator's mailbox. |
| B4 | Basis of the Nov 13, 2025 "within current capabilities" statement | One email from the EDA coordinator. No KMU review exists. |
Of the 70 documents at the top level, 41 were already public on cityofkenyon.gov inside council packets. The email is new.
| Date | Event | Source |
|---|---|---|
| Nov 7, 2024 | Council approves Lehner's hiring, Res 2024-26, $125,500 | ResoLution 2024-26 docx |
| Apr to May 2025 | Five City-KMU agreements signed; council approves May 13 | Agreements PDFs; 4-15-25, 4-23-25 KMU minutes |
| Oct 28, 2025 | Purchase agreement for 551 Engel Dr, $212,000 | Commercial Purchase Agreement (MNCPA).pdf |
| Oct 29 and Nov 5, 2025 | Developer gives load figures to the EDA coordinator | EM Re Firebird-Falcon.pdf |
| Nov 10, 2025 | Coordinator: "Kenyon utilities should have not issues" | 202511101208-Utilities-40.pdf |
| Nov 13, 2025 | EDA hearing; minutes say utilities confirmed demand within capabilities | EDA minutes (council packet) |
| Dec 9, 2025 | Council approves the Firebird agreement | Council packet |
| Dec 16, 2025 | KMU votes to get an estimate and charge Firebird up front | 12-16-25 KMU minutes.docx |
| Dec 17, 2025 | Coordinator forwards the amperage to Eggert and Lehner for the first time | EM Re Firebird-Falcon.pdf |
| Jan 2, 2026 | Lot estimate: transformer $25,000, total $38,250 | Firebird Costs for Preparing 551 Engle Drive.eml.msg |
| Jan 20, 2026 | KMU: "KMU will purchase and install the transformer" | 1-20-26 KMU minutes.docx |
| Jan 28, 2026 | Firebird purchase and development agreement signed | Firebird LLC Purchase and Development-Signed 1_28_26.pdf |
| Mar 26, 2026 | Closing; lot to Falcon Investments LLC | Firebird Request.eml.msg; EDA 3-24-26 minutes |
| Apr 7, 2026 | Coordinator asks for transformer size; "some time" | Industrial Park Lot-KMU questions.eml.msg |
| May 13, 2026 | Xcel/CMPAS meeting: new substation near the industrial park | EMf Jay Anderson 2026-10-20.pdf |
| Jul 16, 2026 | "Randy asked me if we had ever received the amperage." "Not yet." | amperage power.eml.msg |
| Aug 13 to 14, 2026 | ECI Long Range Plan scope; Eggert authorizes | EMf Jay Anderson 2026-10-08.pdf |
| Aug 19, 2026 | County building permit issued; no KMU application | County permit 26-K024 |
| Sep 10, 2026 | Eggert placed on administrative leave | 9-21-26 minutes |
| Sep 18, 2026 | Stamped electrical permit set | Electrical.msg attachment |
| Sep 21, 2026 | Res 2026-34 adopted; KMU vote 2-1 | Resolution 2026-34 pdf; 9-21-26 minutes |
| Sep 23, 2026 | B&B 750 kVA transformer drawing for KMU | Kenyon customer application.msg attachment |
| Oct 5, 2026 | Anderson: "a new roughly 750 kva load (grow facility)" | EMf Jay Anderson 2026-10-05.pdf |
| Oct 12, 2026 | Lehner on the services agreement: "Was sent to Randy in July" | 2026-6-3 Master Distribution Services Agreement.pdf |
| Oct 13, 2026 | Council meeting account; CMPAS attorney sends blank customer application | Kenyon customer application.msg |
| Oct 19, 2026 | KMU asks IPS for the original purchase order | 750 KVA transformer .msg |
| Oct 20, 2026 | KMU meeting: Eggert disputes the account; $1M reframed; substation $5 to 6M | 10-20-26 KMU minutes.docx |
| Oct 21, 2026 | Transformer delivered | 750 KVA transformer .msg |
| Oct 26, 2026 | Production; coordinator to Lehner: "Found it, Scott." | EM Re Firebird-Falcon.pdf |
Every quotation above is from a document in the zip. File names refer to the inventory.